Back to Blog
Applications and How-Tos

Short Circuit Current Rating (SCCR) and Fuse Selection

Tyler Pecha | October 2nd, 2017

Protecting VFDs from short circuit current is essential when designing an electrical panel. But what exactly is the short circuit current rating (SCCR) of electrical components? More specifically, how is the SCCR calculated?

This post will go through a detailed procedure for determining the SCCR of a system, focusing on the differences between direct and isolation transformer fed systems.

 

What Is an SCCR Rating?

The short-circuit current rating is the maximum RMS (Root-Mean-Squared) fault current an electrical component can withstand at a specified voltage. That rating assumes the component is protected by an overcurrent device, typically a fuse, or held to a defined exposure time. The SCCR rating applies to both individual electrical components and entire electrical assemblies or systems.

Figure 1 below shows an AC current waveform after a fault current situation occurs.

 

short circuit fault chart
Figure 1: AC current waveform behavior after a short circuit fault (Source: Littelfuse, 2007)

 

When selecting the proper fuse, it is important to look at the peak let-through current, Ipeak (Ampere) and nominal melting, I2t (Ampere Squared Seconds), ratings.

The Ipeak value is the peak amount of current a fuse will let through before clearing. The I2t value is the amount of thermal energy required to melt the fuse element.

Figure 2 below shows the Underwriters Laboratories (UL) published maximum allowable Ipeak and I2t values for fuses at 100kA and 200kA fault current levels.

 

ul table maximum allowable fuse
Figure 2: UL maximum allowable Ipeak and I2t values for various types of fuses (Source: Littelfuse 2010)Determining the available short circuit current allows for proper fuse selection within the entire system. Knowing how much current a fuse will let through during a fault current situation helps engineers design safe electrical panels, while at the same time protects connected equipment from fire.

 

Proper fuse selection starts with knowing the available current at each point in the system. That number determines how much current a fuse will allow through during a fault and whether the equipment downstream remains protected from fire.

The primary role of the fuse is to prevent equipment fire, not to protect the equipment itself from damage. The available short circuit current at a given point in the electrical system can be determined by reviewing the components which are upstream from the electrical supply point.

 

SCCR vs. AIC: What’s the Difference?

SCCR and AIC are often confused when it comes to panel design documentation. However, they are not the same thing.

AIC (Ampere Interrupting Capacity):
• Applies to overcurrent protection devices, including fuses and circuit breakers.
• Describes the maximum fault current a protective device can interrupt without failing
• It is a device-level rating

SCCR
• Applies to the component or assembly that’s being protected
• Describes how much fault current that component or system can survive when the protective device does its job
• It is an equipment-level rating

 

How They Work Together

AIC represents what the fuse can handle while SCCR represents what the drive, panel, or assembly downstream can handle. A 100kA-rated fuse, for example, does you no good if the block behind it is only rated for 10kA.

In other words, the SCCR of a panel cannot exceed the SCCR of its lowest-rated component. The fuse or breaker protecting a branch must have an AIC rating at or above the available fault current at that point in the system.

 

4-Step SCCR Calculation Process

Calculating SCCR for a motor control system follows a consistent process regardless of system size.

• Step 1: Determine the SCCR of each component in the power circuit. Every device — drives, contactors, distribution blocks, terminal blocks — has a published SCCR on its label or in manufacturer documentation. Any unmarked component defaults to 5kA per UL 508A, which can immediately become the limiting factor for the entire panel.

• Step 2: Identify available fault current and evaluate feeder-level protection. Determine available fault current from your utility or upstream transformer data. Then assess whether current-limiting fuses or breakers at the feeder level reduce the fault current seen by downstream components.

• Step 3: Determine the system SCCR. The system SCCR is the lowest value among all branch circuit component SCCRs and feeder-level component SCCRs. If current-limiting protection is in place at the feeder, the modified let-through current applies to everything downstream.

• Step 4: Verify the overcurrent device let-through current does not exceed the system SCCR. The peak let-through current of your fuse or breaker, at the available fault current level, must not exceed the system SCCR. If it does, select a different fuse class, a lower fuse rating, or make an upstream change to limit available fault current.

If the let-through current of your overcurrent device exceeds the system SCCR, you either need a different fuse class, a smaller fuse rating, or an upstream change to limit available fault current.

 

Worked Example: Direct-Fed System

The SCCR rating of the motor control system is determined by examining the maximum ratings of the individual devices connected to the individual branch circuits. The device with the lowest rating becomes the limiting factor.

Figure 3 below shows an example of a branch circuit diagram fed by a 460V three phase supply.

 

three phase branch circuit diagram
Figure 3: Example Three phase branch circuit diagram

 

The SCCR of Branch 1 is 10kA due to the SCCR value of the molded case circuit breaker (MCCB). Whereas the SCCR of Branch 2 is 15kA resulting from the MCCB. Therefore, Branch 1 is the limiting factor. This motor control system can be fed by a circuit having a maximum capacity of 10kA.

 

Apply Current-Limiting Fuses

The feeder circuit consists of a fusible switch rated at 200 kA, which is in turn connected to a distribution block rated at only 10 kA. Therefore, the distribution block limits the feeder to a 10kA rating.

However, the fuses placed in the fusible switch can be selected such that they limit the available peak current. The combined FLA of the system requires a 60A fuse. As an example, selecting an RK5 60 amp fuse would limit the peak let-through current to 21kA when connected to a system capable of 100kA as defined by Figure 2.

On the other hand, this is 11kA more current than what the branch circuits are capable of handling.

A better choice would be a Class J fuse with a peak let-through current of only 10kA. Using the 60A Class J fuse, the available peak current on the load side of the fuse is only 10kA, which then satisfies the 10kA limitation of the distribution block and the MCCB in Branch 1. The result is that the complete system can be connected to a supply having a 100kA rating.

It is important to note that fuse manufacturers often publish lower peak let-through values for their fuse products than what is listed in the UL table in Figure 2.

But, when designing the distribution system, the UL values must be utilized rather than the manufacturer specific values as these are considered the worst case.

 

Selecting the Right Fuse

The primary role of the fuse in this context is to prevent equipment fire, not to protect the equipment from damage. That distinction matters when selecting fuse type and size.

When selecting a fuse, two ratings drive the decision:

• Ipeak: the peak current the fuse allows before clearing. This value must not exceed the SCCR of the downstream components.

• I²t: the thermal energy (in ampere-squared seconds) required to melt the fuse element. Lower I²t means the fuse clears faster and dumps less energy into the circuit.

UL publishes maximum allowable Ipeak and I²t values for fuses at 100kA and 200kA fault current levels by fuse class. These are the ceiling values for design purposes.

For most industrial panel applications involving VFDs, consider Class J High-Speed fuses.

They perform comparably to semiconductor fuses and offer tighter let-through characteristics than standard Time Delay Class J fuses. This matters especially in transformer-fed systems where available fault current may be limited.

 

Isolation Transformer-Fed Systems

AC motor control systems being fed by an isolation transformer have fuse type and size dictated by the available short circuit current of the isolation transformer. To select the proper fusing, the available short-circuit current of the transformer must first be determined.

Maximum permissible fuse sizing is dictated by UL and further by the National Electric Code, NEC. According to the National Electric Code (NFPA-70 or CSA 22.1), per Article 450-3(B) of NFPA-70 (similar statements can be found in CSA 22.1), the maximum fuse size is defined in table 450.3(B) with a rating not greater than 125% of the rated secondary current.

In the case of multiple secondaries, it is the rated value of the winding with which the unit is supplied from. Because the transformer’s required fuse rating is often lower than the AC motor control’s tested maximum, the transformer fusing governs.

 

Verifying Fuse Clearing Time

One more step must also be taken to ensure proper fuse selection. An isolation transformer limits the available short circuit current of the system. With a limited available fault current, the peak current may not be enough to clear the fuse in a fault situation.

For adequate protection, the fuse must clear instantly, with the upper clearing time limit within the first half cycle of an AC current wave (i.e., approximately 10mSec). Therefore, it is necessary to determine the amount of short-circuit current available on the secondary winding of the isolation transformer.

 

Worked Example: Isolation Transformer-Fed System

Consider the following example for proper fuse sizing. A 460V application is using an isolation transformer rated for 34kVA, a KEB Harmonic Filter, KEB R6 regen unit, and KEB F6 VFD.

Since the available short circuit current of the isolation transformer is unknown, it must be calculated. To calculate the transformer secondary rated current, along with the collective available short circuit current, the following equations can be used.

Expressed formally:

secondary current calc - 1a
1a – Secondary current calculation example

 

The secondary current can be calculated using the 34kVA power rating of the isolation transformer fed with a 460V line, yielding a secondary rated current of approximately 42.6A.

secondary current calculation - 1b
1b – Secondary current calculation example

 

The fuse size must not be greater than 125% of the secondary rated current. Expressed formally:

transformer secondary - 2
2 – Secondary current calculation example

 

From Equation 2, 125% of the secondary rated current is 53.3 amps.
Next, the available short-circuit current at the transformer must be determined. This can be calculated by determining the collective available short circuit current.

 

Collective Short Circuit Current

To protect against short circuit currents, limited by an isolation transformer, the required current a fuse needs to clear instantly needs to be evaluated. To do this, the collective available short circuit current of the mainline and isolation transformer must be determined.

To calculate the available short circuit current of the mainline and transformer, the full sequence of calculations is shown below:

Transformer secondary 3a
3a – Secondary current calculation example

 

Assuming the mainline has a current of 400 amps and an impedance of 0.5% Eq. (3a) becomes the following…

transformer secondary 3b
3b – Secondary current calculation example

 

Next, the current of the transformer can be calculated by the following equation…

transformer secondary calculation 4a
4a – Secondary current calculation example

 

Assuming the transformer has a rated power of 34 kVA Eq. (4a) becomes the following…

4b
4b – Secondary current calculation example

 

Next, the available short-circuit current of the transformer can be calculated by the following equation…

transformer secondary 5a
5a – Secondary current calculation example

 

Assuming the transformer has a rated impedance of 5% and a current of 43 amps Eq. (5a) becomes the following…

secondary current 5b
5b – Secondary current calculation example

 

Now that the available short circuit current of the transformer has been calculated, the proper fuse must be selected. To select the proper fuse size, consult with the manufacturer’s published fuse blow curves.

 

Fuse Blow Curves

Fuse manufacturers typically publish self-tested performance data for their fuses to help customers select the proper size. This performance data typically varies between manufacturers, so be sure to consult the manufactures’ data before selecting a fuse.

For this application, Class J fuses are to be used.

 

mersen class J fuse melt
Figure 4: Time Delay Class J Fuse Melting Time – Current Curve (Source: Mersen Electrical Power, 2002)Figure 5 below shows the performance data for Mersen High-Speed Class J fuses (Mersen Electrical Power, 2003).

 

Mersen High Speed J fuse melt
Figure 5: High Speed Class J Fuse Melting Time – Current Curve (Source: Mersen Electrical Power, 2003)

 

Looking at the Figure 4, Time Delay Class J Fuses rated for 50A and 60A require 800A and 950A, respectively, for 10ms to clear. In comparison, as seen in Figure 5, High Speed Class J Fuses rated for 50A and 60A require 400A and 500A, respectively, for 10ms to clear.

Time Delay Class J fuses do not provide adequate short-circuit protection in this application. That’s because the available fault current may not be high enough to clear the fuse within one half-cycle. The High-Speed Class J fuses are a much safer option by providing the required clearing currents down to 1ms. According to Figure 5, the 50A and 60A fuses require 675A and 850A, respectively, for 1ms to clear.

Recall that the available short circuit current from the isolation transformer is 860A. The 60A High Speed Class J Fuse is marginally close (850A) to the available short circuit current from the isolation transformer (860A). Given this information, the 50A High Speed Class J fuse is the best choice to provide adequate short circuit protection.

For the best protection of electrical components, KEB recommends using Mersen High Speed Class J fuses. These fuses can take the place of a standard Class J fuse; however, they perform like a semiconductor fuse.

 

SCCR Ratings for KEB Components

KEB publishes SCCR documentation for its drives and motors. When you’re building a panel around KEB components, this data should be pulled early in the design process — before fuse selection — so that branch circuit ratings can be established before you’re locked into a configuration.

For KEB drives, SCCR data is included in the product documentation available on each product page. The F6 and the S6 servo drive, for example, includes SCCR specifications that must be matched against your fuse selection and available fault current.

If you’re designing a panel for a material handling application — conveyors, hoists, sortation systems — SCCR compliance often comes up during UL 508A panel certification. Having component-level SCCR documentation from the drive manufacturer on hand before that review saves significant time.

 

Frequently Asked Questions

What is the minimum SCCR for an industrial control panel?
UL 508A requires a marked SCCR on all industrial control panels. For most industrial applications, the requirement is 65kA or 100kA. This will depend on the available fault current at the point of installation.

What’s the default SCCR for unmarked components?
Per UL 508A, unmarked components automatically default to 5kA. This can be a limiting factor in a panel SCCR calculation, since it pulls the entire assembly down to that rating.

Does a VFD have an SCCR rating?
It does. A VFD’s SCCR depends on the overcurrent protection device paired with it. So, the same drive may carry different values of SCCR depending on the fuse class and rating.

Can a panel’s SCCR be raised after installation?
Sometimes. Upgrading to a current-limiting fuse with lower let-through characteristics is the most common method. Any change requires full system re-evaluation and panel re-marking.

If you have questions about SCCR data for a specific KEB component, reach out through the form below.

Contact Us

Let's Work Together

Connect with us today to learn more about our industrial automation solutions and how to commission them for your application.

"*" indicates required fields

This field is for validation purposes and should be left unchanged.